How to use the critical path method in project management
The critical path method helps you to sequence activities, calculate realistic timelines for projects and finish projects on time. Find out how it works.
Summary
- The critical path is the longest sequence of dependent tasks that determines your project timeline - If cooking dinner requires a 1-hour roast and 20 minutes of vegetable prep happening simultaneously, the roast defines when you eat, not the vegetables. Focus your attention on these time-determining activities.
- Use the formula (a+4m+b)/6 to estimate realistic task durations - Get three time estimates from your team (best case, most likely, worst case), weight the most likely scenario four times heavier, then average. This gives you working numbers instead of wishful thinking.
- Float reveals which tasks can slip without derailing your project - Calculate early/late start times using forward and backward passes. Tasks with zero float are on your critical path and need the most management attention. Tasks with float give you breathing room.
- Fast-tracking means overlapping dependent tasks, not just throwing more resources at them - Start warming the dinner plates before the food finishes cooking, not after. Look for preparation steps that can happen earlier without compromising quality. Manage projects better with Tallyfy
A friend once said that the critical path method is used because “Whatever you do, something else has to happen first.” That’s a trifle overly simplistic, but it’s a good starting point for an introduction to the critical path method. Here, we will take a rather more in-depth look at this methodology. Don’t be put off by the math! It’s easier to master than it looks!
What is the critical path method?
In its simplest form, a project will consist of a single sequence of activities that absolutely has to happen within a certain timeframe. Otherwise, you run the risk of the project not being completed on time.
More often than not, those, some of these activities are happening at the same time, and if one is delayed, the entire project might be delayed. And as you probably already know, delays can be very expensive! There will also be activities that have a rather more flexible schedule.
You need to complete them, but their completion date is not as critical to timely completion of the whole project as that of other activities. Cooking a meal provides a good example.
You want your meat and veg to be ready at about the same time. But it does not matter if you lay the table an hour early or whether you lay it five minutes before you are ready to serve dinner. The timing of your meat and vegetable preparation is critical, the time of laying the table is less critical.
The simplest definition of the critical path method would be: “The order and schedule of activities that determine how long a project will take.” It’s worth noting the difference between critical and non-critical activities. It’s the critical ones that define the timeline.
Using our example, how long does it take you to prepare dinner? The time you need to lay the table will be the least of your time-bound concerns so that that schedule can be a lot looser. Laying the table does not “determine how long” cooking the dinner takes.
Once you understand which tasks define your timeline, the next challenge is actually tracking them. Here is how workflow management software can help you keep critical activities visible and on schedule.
Workflow Made Easy
What does the critical path method look like?
Visually, the critical path method is a diagrammatical representation of the entire project. You can use the diagram to get an overview of what is going on, check schedules, and as project manager, you can intervene as necessary to keep the project on track once it is up and running. The best features of this representational method include:
- Clear identification of the “critical” or vital tasks that require the most management attention. You want to finish on time. Which activities are the determining factors that show whether you are likely to do so? Knowing which ones they are, gives you priorities for intervention.
- Identify areas for fast-tracking the project. Let’s say you want to get finished faster than the initial timeline suggests. Which tasks can you speed to ensure early completion? The “critical” tasks ultimately determine the “when” and they are the ones you need to support if you want a shorter completion time.
- The critical path method helps managers to see whether projects are going as planned. At any time during project execution, the manager can see which tasks are taking more or less time than expected. This allows for the updating of schedules and a comparison against the initially-planned critical path. During the project, managers can plan to overcome any delays caused by deviations, and afterward, they can use the information to help plan for future projects of a similar nature.
Critical path method in practice
So far, so good. We have a good understanding of what the critical path method is and why it’s a good idea to use it. But what do you need to do to compute a critical path for your project? Let’s use a six-step approach.
Which activities does the project entail?
Before you start thinking about what is critical and what is not, list all the activities that your team will complete to finalize the project. At this stage, you don’t have to go into too much detail, in fact, you shouldn’t.
You want an overview that shows you the big picture. Once you have that, you can get to work on the finer details. So, you are cooking dinner.
You need to cook the meat, cook the veg, and serve the meal. Once you know this, you can check out the recipes and spit the “higher level” activities (cook meat, cook veg) into smaller steps that include all the details.
What depends on what?
Some activities can’t begin until the previous activity has been completed. When making dinner, you cannot cook your veg until you have washed, peeled and chopped it. Your project is probably a great deal more complex than just preparing a supper, so ask yourself:
- If I want this task done, which task must happen first?
- Which other tasks should finish at around the same time?
- What happens next?
Create a network diagram
Now you know which activities needed to complete the project depend on others, you can sketch out their interrelationship and the order in which they must be carried out.
This is your most basic critical path analysis chart. It gives you an at-a-glance version of your project’s path to completion, but it’s far from finished yet.
You know the what, now for the when
In reasonably simple, short-term projects, you might just go for a guesstimate time frame for the completion of each step. However, suppose you want a greater degree of certainty and that the project is rather complex, you need three different time estimates.
These are given standard symbols that can be fitted into simple equations. a is the estimate if all goes well and there are no hitches. m is the estimate that seems most likely.
b is a worst-case scenario. What is the longest time it will take to get this step done?
As a project manager, you will need to get these figures from the people who know the specific task best. You do not need to be an expert on every activity your project entails, but you do need to rely on the expertise of your project team. Without an experience-based estimate of each of the three different time frames, your figures will be meaningless. At Tallyfy, we’ve seen that project teams consistently underestimate the worst-case scenario until they have been burned by it at least once - whether it’s media production companies managing 60-task workflows or professional services firms tracking client deliverables.
Now that you have your variables (a, m and b) you can use these tested formulae to decide on a time frame for each step. Estimated time = (a+4m+b) / 6 As you can see, the time identified as the most likely is given more weight than the shortest or longest possible times in this formula.
It is multiplied by four in the equation and added to the fastest and slowest likely times before you calculate an average by dividing by six. The triangular distribution another approach will give you a slightly different time frame as its answer and does not add weight to the likeliest time identified. Instead, it estimates time-based on a straightforward average between the best, likeliest and slowest time-frames.
Estimated time = (a + m + b) / 3 Whichever method you choose, you will now have a set of time frames for each activity in the project, and it is time to move on to the next step.
Which is the critical path?
There are two techniques for identifying the critical path. Remember, this is the path that determines just how long your project will take.
That means that if you run parallel activities, the real critical path represents the sequence of activities that take the longest time to complete. Your teams will finish the other activities in the chain with ease before the critical path has run its course. As a project manager, making sure that the most sensitive path (the one that takes the longest time) does not go off track will keep your project running on time.
When determining the critical path chain of events, remember that some activities will consist of more “nodes” (the boxes indicating what the activity is) but still take less time than some of the chains with fewer boxes. Back to the simple project of making dinner: the roast will take an hour, but although preparing the veg involves more steps, it will not take you as long to complete.
If you do not want dinner to be late, you need to base the time you plan for cooking it on the dish that takes the longest time, in this case, the roast. The forward pass and backward pass technique offers another way to look at it.
The diagram above illustrates a forward pass.
Activity A has no predecessor, so we know that its team must be finished within the estimated time and that it is not influenced by preceding steps. Activity B, however, follows activity A.
We estimate that it will be complete after A’s estimated time has passed, and Bs estimated time as run. With the backward pass, you will begin at the end of your project and work backward. This time, you will incorporate “float.” The Float is the difference between the time you have to finish part of a project and the total “early finish” times you calculated.
You can add this slack to figure out late completion dates for all activities. Now that you have the early and late start and finish times, you can fill them in below each node on the representation, and you will also be able to identify the areas that have no float.
These will indicate your critical path. No matter which method you choose, the longest chain of events in terms of time needed is your critical path. If you have several of these, your project becomes more sensitive to variation.
There are more critical activities taking place at once, and more activities mean a greater chance of variance in the schedule.
Run with it and update it as you go
After all this thinking, the time has come to take the plunge. You know what to do, and you know which activities have the greatest importance in ensuring timely completion.
You also need to track the less critical activities, but you have a lot more leeway with them. You have estimated the time you need for each step, and now it is a matter of tracking to see whether activities are finished late, early, or completed in the estimated time. You are, of course, likely to see some variation from your estimates.
If critical chain activities finish early, you might find that you have a new and completely different set of activities that become critical to completing the project on time. Keep analyzing your critical chain throughout so that you know where your critical path activities lie.
If critical activities are running late, the project manager has three options:
- Decide whether there is enough slack for a revised estimate
- Find ways to fast-track the affected activities
- Accept that the project will finish the project late
How to speed projects up using critical path methods
Since you will use the critical path to determine how long the project takes, it usually will not have much if any “float.” If you want to fast-track the project, the critical path is the place to begin looking. You do not necessarily have to throw more resources at an activity in order to get it done faster.
You can look at your diagram and determine whether some activities can start before the previous one is finished. You may not be able to complete them, but you can prepare them for rapid completion once the task it depends on finishes. Let us suppose that your dinner-cooking project involves a serving activity.
As part of this, you need to warm the plates first. If you wait till your food is ready to be served before warming the plates, it will take longer to complete the project.
However, there is nothing to stop you from warming the plates before the food is ready. You still can’t serve the meal before the food is cooked, but when it is, you don’t have to wait for the plates to warm up. Of course, throwing more resources at steps to get them finished faster is an option.
This idea is called “crashing.” However, rushing things by crashing could reduce quality. This matters a lot. Weigh using this approach with caution.
Think of that lovely roast dinner. You could have it ready faster if you microwave it, but do you really want to?
The critical path and management of resources
You will need resources to complete any project. You have a map representing the path to your goal.
You have a critical path that will determine the duration of the project, but you will also need resources. Whether its money, people, or materials, you do not have access to an unlimited amount of resources. You may even find that the availability of resources, rather than time, will probably affect when you can finish your project.
Combine critical chain analysis with your critical path methods to protect your project from delays caused by a shortage of resources. You may find that you have to build in a little extra time so that your project can wait for a resource to become available.
Tools to help you
The critical path method is a way of determining the duration of a project. It provides the parameters for monitoring that the project is on track, and it can be revisited when reviewing a project to see what could have been done better.
There are other diagrams you can use to set out how a project will work and when each task will begin and end. The Gantt Chart is still widely used, and some project managers like using a hybrid between the critical path method and PERT. You will still need to set up reporting duties and monitor progress carefully, though, and that can be a complex task on its own.
A project is a process, however, and processes, once planned, can be automated and monitored using the right software. Tallyfy is a versatile process management tool that will help you to keep on top of your projects by monitoring everything down to the last sub-process.
Templates for projects with critical dependencies
You will get early warning of where delays are cropping up, where bottlenecks you did not expect are affecting timelines, and you will be able to see just how this affects the critical path your project follows. Feedback we have received from nonprofit organizations managing 60-day member onboarding processes suggests that this visibility - knowing where people are falling behind and require intervention - is what separates projects that recover from those that spiral. Spot when your critical path has shifted to a new area and be ready to respond with management intervention where and when it is needed most. Use the easy way to make the critical path method work for you.
About the Author
Amit is the CEO of Tallyfy. He is a workflow expert and specializes in process automation and the next generation of business process management in the post-flowchart age. He has decades of consulting experience in task and workflow automation, continuous improvement (all the flavors) and AI-driven workflows for small and large companies. Amit did a Computer Science degree at the University of Bath and moved from the UK to St. Louis, MO in 2014. He loves watching American robins and their nesting behaviors!
Follow Amit on his website, LinkedIn, Facebook, Reddit, X (Twitter) or YouTube.
Automate your workflows with Tallyfy
Stop chasing status updates. Track and automate your processes in one place.